Project Details

Client
ROYAL BOROUGH OF GREENWICH
Location
GREENWICH
City
CITY OF LONDON
Contract Type
JCT Design & Build
Duration
25 WEEKS
Valuation
£1.4 MILLION
Category
Education
Size
300m²

  • 01

    OVERVIEW

    This project involved the rapid co-ordination of the final design elements, including a new solar glazed roof to the schools DT Room, final MEP works to ensure the system was fully functioning and the fitting out of the schools new Admin Office.

  • 02

    WORKS METHODOLOGY

    Works comprises of installing a solar glazed roof to the DT Room which required removal of the existing arrangement together with the reinstatement of flashings and existing weathering.

     

    Completion of the final elements or partitions, ceilings and decorations, final ironmongery to doors, a new entrance reception hatch to comply with DDA requirements, new blackouts blinds to the classrooms were included also.

    In addition installation of convector heaters together with plumbing modifications to allow easy installation, completion of the ventilation extract system to the WC’s and offices, completion of the ventilation system with cooker extracts to the DT Room, final electrical and data works to the various offices, external glazed canopies and external gate installation and making good were all included in this project.

  • 03

    OUTCOME

    This project was completed on schedule and on budget.

    The client was happy with the finished works and the collaborative approach the team had throughout the project has led to an excellent relationship being developed with the client.