Our Experience
The Alcema team have been involved in numerous projects ranging up to £30 million in value. Regardless of size and scope, we are dedicated to deliver every build to exceptional standard.

MARKS AND SPENCER
The team have successfully completed several projects for Marks and Spencer and they were assigned the complete refurbishment of The Pantheon, one of Marks and Spencer’s flagship stores located on Oxford Street, London.
Dating back to the 1930’s, the building presented several legacy issues, including asbestos-containing materials. Through exemplary communication with the store team, we were able to phase the required works whilst causing minimal disruption to staff and customers.
-
DURATION
14 weeks
-
CONTRACT TYPE
JCT Minor Works with Design
















NORTHAMPTON GENERAL HOSPITAL
This project involved the construction of a new cardiology and nuclear medicine facility for Northampton General Hospital. The works involved the implementation of a complex steel frame in between and on top of live departments using small size pile rigs. Multiple meetings between all parties involved ensured a superb finished build for the hospital with minimal disruptions to its day-to-day activities.
-
DURATION
70 weeks
-
PROJECT VALUE
£13 million
-
COLLEAGUES
Paul Reeve and Marcus Darcy












ST MICHAEL’S CATHOLIC SCHOOL
This project encompassed the phased development of a ‘satellite’ secondary school of St Michael’s in Aylesbury. A temporary school, accommodating 120 Year 7 pupils, was built while the construction of the permanent school was in progress.
The final result was delivered in 2020; the works spanned exactly two years, with a total project value of £30m.
-
DURATION
104 weeks
-
PROJECT VALUE
£24 million
-
COLLEAGUES
Chyrryl Culley

THE NATIONAL MEMORIAL ARBORETUM
The Arboretum in Alrewas is a British site of national remembrance. The visitor centre was expanded to accommodate a higher volume of visitors – up to 500,000 more. The project involved the demolition of the existing building and the construction of a new hybrid steel and glued laminated (glulam) beams structure.
Throughout the works, the site remained live with no disruptions to the daily service.
-
DURATION
54 weeks
-
PROJECT VALUE
£10.8 million
-
COLLEAGUES
Marcus Darcy

HOTEL INDIGO
The project involved refurbishing all the existing rooms of this 16th century, Grade II listed property. This included stripping back the historic Tudor building to its timber frames in order to protect and preserve it for posterity. The logistics of the project were extremely challenging on all sides and were coupled with the application of heritage restoration requirements.
-
DURATION
Ongoing, Phased over two years
-
PROJECT VALUE
£13.5 million
-
COLLEAGUES
Paul Reeve





